Week 16: Finished framing first floor interior walls and set glulams.
SATURDAY
It has felt like things have been moving a little slower so we were really looking forward to getting a lot done this weekend. However a couple of the posts that were delivered were the wrong size and between having to run to town to get those and all the last little things that needed to get squared away we didn't get quite as far as we'd hoped. We did however set our final interior walls on the first floor and we got to set our first glulam which was pretty exciting.
Sadie helped the kids paint bird houses while we worked.
TUESDAY
Tuesday we finished setting our other two glulams and started laying out for the floor joists.