Friday, February 16, 2024

Troyer Addition: Week 46-48

January 13, 2024

Week 46-48: Week 46 was a no work recover from sickness/snow week and week 47 was pretty slow too.  We're struggling to get back into pump out mode after the holidays.  But we did get a new generator and got the tile in the upstairs bathroom started.  Week 48 was tile in the upstairs bathroom, we got our doors and trim delivered, and the fire sprinkler company installed our water tank and cover plates.

January 20, 2024






The whole crew came up to watch him lay the first tile.


January 27, 2024
Still so much to do but tile on the floor is complete. ✔

Doors and trim delivered. ✔

Fire sprinkler tank installed. ✔