Troyer Addition - Week 18

 July 1, 2023

Week 18: Finished floor joists and sub floor, new septic system installed, and plywood on walls started

SATURDAY

Brandon took the week of and worked some long days getting getting things done on the house.  He spent the first part of the week finishing up the floor joists and all the blocking between the joists.   He also started laying the sub floor.








WEDNESDAY
Wednesday Action Drain showed up and with A LOT of equipment and started digging for our new septic system and tank.







Our poor goats had to be locked up for 3 days but thankfully they did okay in our little shed.








FRIDAY
On Friday we started hanging the plywood on the walls which was an exciting way to wrap up the week.